Generator set factory acceptance test checklist

Write the test sequence, limits and evidence requirements into the purchase documents so the buyer and factory can agree what counts as a pass.

Motori a gas e apparecchiature di distribuzione
Generator set application illustration

Agree on the test conditions before the witness date

Record the set configuration and serial numbers, fuel, ambient conditions, load bank and instrument calibration. Agree the load sequence, measurement points, stabilization or recovery criteria, and which protections or alarms will be demonstrated. Refer to the applicable test method in the contract.

Close deviations before shipment

Ask for time-stamped readings or plots where relevant, a signed result sheet and a list of open items with owners. Separate factory checks from site checks such as transfer with actual switchgear, installed ventilation, and behavior with real project loads.

Factory acceptance witness checklist
StageAgree or observeRetain
Before testingConfiguration, instrument and procedure reviewApproved procedure and calibration records
During testingLoad steps, voltage and frequency, alarmsMeasured data and witness notes
Before releaseDeviation disposition and retest scopeSigned report and open-item register

Next procurement step

Ask the supplier for a draft FAT procedure and mark the witnessed tests before signing the order.