ResourcesGenerator set procurement articles
Generator set factory acceptance test checklist
Write the test sequence, limits and evidence requirements into the purchase documents so the buyer and factory can agree what counts as a pass.

Agree on the test conditions before the witness date
Record the set configuration and serial numbers, fuel, ambient conditions, load bank and instrument calibration. Agree the load sequence, measurement points, stabilization or recovery criteria, and which protections or alarms will be demonstrated. Refer to the applicable test method in the contract.
Close deviations before shipment
Ask for time-stamped readings or plots where relevant, a signed result sheet and a list of open items with owners. Separate factory checks from site checks such as transfer with actual switchgear, installed ventilation, and behavior with real project loads.
| Stage | Agree or observe | Retain |
|---|---|---|
| Before testing | Configuration, instrument and procedure review | Approved procedure and calibration records |
| During testing | Load steps, voltage and frequency, alarms | Measured data and witness notes |
| Before release | Deviation disposition and retest scope | Signed report and open-item register |
Next procurement step
Ask the supplier for a draft FAT procedure and mark the witnessed tests before signing the order.
Technical references
Generator set procurement articles
Diesel vs gas generators for industrial sites
Start with the fuel that can reliably reach the set during the hours it must run. Then compare both packages against the same load profile and operating scenario.
Prime vs standby generator ratings
Select the duty rating from how the set will run, then compare site-rated electrical output under that duty.
What fuel data belongs in a gas generator RFQ?
Identify the gas and its variability at the proposed equipment boundary. A fuel name alone gives the supplier too little information to confirm a configuration.
How to compare generator set quotations
Put competing quotes on a shared technical and commercial basis before ranking their prices.
How to specify data center standby generator sets
Start with the power restoration sequence and the loads each set must accept. Use these inputs to review the generator and switchgear interface with the project electrical team.