What fuel data belongs in a gas generator RFQ?
Identify the gas and its variability at the proposed equipment boundary. A fuel name alone gives the supplier too little information to confirm a configuration.

Describe the source and sampling conditions
Share a recent gas analysis, sampling date and point, and any known seasonal or process-driven variation. Include reported composition, heating value with its basis, moisture and contaminants. Keep lab units and reference conditions with the report.
Request a written fuel acceptance envelope
Give minimum, normal and maximum pressure and available flow at the agreed tie-in point, including expected changes during startup or a load increase. Ask the supplier to state allowable inlet conditions, required treatment, responsibility for the gas train and any output restrictions for the supplied fuel.
| Input | What to send | What to ask for |
|---|---|---|
| Composition | Lab report, source and sample date | Acceptable variability and contaminants |
| Delivery | Pressure and flow range with units | Required conditions at the set inlet |
| Interfaces | Tie-in drawing and operating profile | Treatment and gas-train supply boundary |
Next procurement step
Send an available lab report with your inquiry and mark missing values as pending.
Technical references
Generator set procurement articles
Diesel vs gas generators for industrial sites
Start with the fuel that can reliably reach the set during the hours it must run. Then compare both packages against the same load profile and operating scenario.
Prime vs standby generator ratings
Select the duty rating from how the set will run, then compare site-rated electrical output under that duty.
How to compare generator set quotations
Put competing quotes on a shared technical and commercial basis before ranking their prices.
Generator set factory acceptance test checklist
Write the test sequence, limits and evidence requirements into the purchase documents so the buyer and factory can agree what counts as a pass.
How to specify data center standby generator sets
Start with the power restoration sequence and the loads each set must accept. Use these inputs to review the generator and switchgear interface with the project electrical team.