ResourcesGenerator set procurement articles

Prime vs standby generator ratings

Select the duty rating from how the set will run, then compare site-rated electrical output under that duty.

Máy phát khí và thiết bị phân phối
Generator set application illustration

Describe a representative operating cycle

A backup set starts when the normal source fails. A prime-power set may supply a changing load as the main source. If the site expects sustained operation at a steady load, ask for the continuous-duty basis. State annual hours, average and peak loads, and the largest single step.

Normalize the numbers before comparing bids

Ask for the rating definition, allowable hours and average-load limits, plus any overload allowance. Compare electrical kW and kVA at the same power factor, voltage, frequency and site conditions. Ask which auxiliary loads are included when the supplier states usable output.

Map duty to the rating you request
Operating patternRating to discussVerify in writing
Normal supply interruptionStandbyOperating restrictions and expected outage pattern
Primary source with varying demandPrimePermitted average load and overload policy
Sustained steady outputContinuousOutput at site conditions and auxiliary loads

Next procurement step

Attach a daily load profile and expected annual operating hours to the inquiry.